A force majeure clause gets read exactly once with care, and that is after something has gone wrong: the port is shut, the factory is flooded, the client has stopped paying because a lockdown stopped their customers. By then, the wording you skipped is the only thing standing between you and a damages claim.
Here is the short version for India. A force majeure clause is a contractual excuse. It says that if a listed event outside both parties’ control stops one of them from performing, that party is not in breach for as long as the event lasts. Indian law has no standalone statute for it. The clause works because Section 32 of the Indian Contract Act, 1872, treats it as a contingent contract, and the courts enforce it as written. If you have no clause, you are left with Section 56, the doctrine of frustration, which is much harder to use and, when it works, ends the contract altogether.
The rest of this article covers what Indian courts have actually decided (not what the textbooks say they might), how a force majeure clause differs from frustration, what the clause does with money and rent, five sample clauses you can compare against your own, a drafting checklist, and what to do in the first week after an event.
What a force majeure clause means
“Force majeure” is French for superior force. The idea is old: a promise should not bind you when something no one could have prevented makes keeping it impossible. English common law never recognised it as a doctrine, which is why English contracts spell it out. India took the English route. If your contract does not have a force majeure clause, you cannot import one from the phrase.
A force majeure clause has four jobs:
- It defines which events count.
- It says what the affected party must do (notice, mitigation, evidence).
- It says what happens to the obligations while the event continues (suspended, extended, excused).
- It says what happens if the event does not end (a right to terminate after a set period).
Most failures come from a force majeure clause that does the first job badly and skip the other three.
A force majeure clause and frustration are not the same thing
People use the two terms as if they were interchangeable. In Indian law they sit in different sections and behave differently.
| Force majeure clause (Section 32) | Frustration (Section 56) | |
|---|---|---|
| Source | Your contract | The statute, applied by courts |
| Event | Whatever the clause lists | Performance becomes impossible, or unlawful by an event the promisor could not prevent |
| Effect | Usually suspends or excuses performance while the event lasts | The contract becomes void from the moment of impossibility |
| After-effects | Governed by the clause | Restitution of benefits received under Section 65 |
| Difficulty | Depends on wording and facts | High; “impossible” has been read narrowly |
| Notice | Usually mandatory under the clause | No statutory notice, but act promptly |
The key authority is Energy Watchdog v. CERC ((2017) 14 SCC 80), where the Supreme Court held that where a force majeure clause covers the event, the clause governs, and Section 56 has no work to do. In that case, steep rises in the price of Indonesian coal did not qualify: the power purchase agreements had dealt with fuel risk, and the Court would not use Section 56 to override the risk the parties had allocated.
Older authority sets the frustration test. In Satyabrata Ghose v. Mugneeram Bangur & Co. (AIR 1954 SC 44), the Court said “impossible” in Section 56 does not mean literal impossibility. It covers a situation where performance becomes impracticable and useless in view of the object and purpose the parties had in mind. The test is whether the event strikes at the root of the contract. A wartime requisition that merely delayed the transaction did not. In Alopi Parshad & Sons v. Union of India (1960), the Court said that a promise does not become impossible just because it has become more onerous or expensive.
So, on the first big question, whether rising costs excuse you: no, not under a force majeure clause that is silent about price, and not under Section 56.
The five things you have to prove
Reading the case law together, a claim under a force majeure clause needs five things. A tribunal will check them in order, and failing any one is enough.
- The event is listed or falls within a catch-all. A clause that names floods, war and epidemic will not automatically cover a cyber attack unless it has general words (“any other event beyond the reasonable control of the party”) and the court accepts that the general words reach it.
- The event was beyond your reasonable control and not caused by your own fault or by something you could have avoided.
- It actually caused the non-performance. Not “made it harder”. Many clauses use the word “prevents”, and courts take it literally. In Steel Authority of India v. Norvic Shipping North America (Delhi High Court, judgment of 22 September 2026), the court upheld an arbitral award rejecting a COVID-19 and cyclone plea because SAIL had not shown that discharge was actually hindered. The clause referred to a party being “prevented” from performing, and the evidence did not show prevention. Government orders had in fact declared cargo handling an essential service.
- You had no reasonable alternative and you tried the ones available. Costlier is not impossible.
- You followed the procedure in the clause: notice, evidence, updates, mitigation.
If you were already in default before the event, expect the claim to fail. In Halliburton Offshore Services v. Vedanta (Delhi High Court, May 2020), the court refused to let a party rely on the pandemic where its contractual deadlines had fallen before the outbreak.
What courts have actually done with a force majeure clause
These are the decisions I would read first. I have noted where I only have a secondary summary.
| Case | Court and year | What happened |
|---|---|---|
| Satyabrata Ghose v. Mugneeram Bangur | Supreme Court, 1954 | Frustration needs impracticability going to the root; delay and a war known to the parties were not enough |
| Alopi Parshad v. Union of India | Supreme Court, 1960 | Onerous or costlier performance does not discharge a contract |
| Energy Watchdog v. CERC | Supreme Court, 2017 | Clause governs over Section 56; price rise in imported coal was no excuse; “Law” in the clause meant Indian law only |
| GEA EGI v. BHEL | Delhi High Court, 2016 | Civil war in Syria excused physical construction work but not payment for equipment already made (as summarised by commentators) |
| Phosphate Company v. Emirates Trading Agency | Calcutta High Court, 2016 | US sanctions on Iranian banks made procurement difficult but did not make performance impossible |
| Standard Retail v. G.S. Global Corp | Bombay High Court, April 2020 | COVID plea rejected: steel distribution was an essential service and the lockdown was temporary |
| Halliburton v. Vedanta | Delhi High Court, May 2020 | Pandemic cannot excuse a party already in default; each case turns on its own facts |
| MEP Infrastructure v. SDMC | Delhi High Court, June 2020 | Relief granted; court relied on a Ministry of Road Transport circular of 19 February 2020 and excused late notice because the other side had acknowledged the event |
| Rashmi Cement v. World Metals & Alloys | Delhi High Court, June 2020 | Government circulars were not binding on private parties; balance of convenience weighed against the claimant |
| Polytech Trade Foundation v. Union of India | Delhi High Court, May 2020 | Ministry advisories were not mandatory and did not stop contractual charges |
| NHAI v. Sahakar Global | Delhi High Court, 2021 | A GST change was upheld as force majeure because the contract covered changes in law with a material adverse effect |
| Airports Authority of India v. Delhi International Airport | Delhi High Court, March 2025 | Award upholding DIAL’s COVID force majeure claim survived a Section 34 challenge; court called a force majeure clause an “eclipse provision” that suspends other terms while the event continues, and said no one could have foreseen how long the pandemic would last |
| Steel Authority of India v. Norvic Shipping | Delhi High Court, September 2026 | COVID and cyclone pleas failed for want of proof of actual prevention |
The pattern is consistent. Courts do not take disruption as proof of prevention. They want a line from this event to this failure, with evidence, and they look hard at whether the party had already breached or had alternatives.
Money, rent and payment obligations under a force majeure clause
This is where businesses are most surprised. An obligation to pay money is rarely “prevented” by a flood or a lockdown, because paying is still possible, only harder. In GEA EGI v. BHEL, the court treated physical work as excused but payment for goods already supplied as owed. Unless the force majeure clause says that payment obligations are covered, assume they are not.
Tenants face the same question. A shop that cannot open during a lockdown has a bad trading year, but unless the lease has a rent-abatement or force majeure provision that fits, the landlord’s right to rent does not disappear. If you draft commercial leases, put the position in writing. Our guide to the commercial lease agreement shows where this sits among the other clauses, and the comparison of a rent agreement and a lease agreement explains why the document type matters.
Government circulars are not a substitute for a force majeure clause
During COVID-19, the Department of Expenditure issued an office memorandum on 19 February 2020 saying supply-chain disruption from the pandemic could be treated as a natural calamity for government procurement, and other ministries issued similar notes. In MEP Infrastructure a High Court gave relief on that basis, but in Rashmi Cement and Polytech Trade other benches said such circulars and advisories do not bind private parties. If your contract is with a private counterparty, do not count on a circular to rescue the force majeure clause you did not draft.
Five force majeure clause examples to compare against yours
1. The weak, generic force majeure clause
“Neither party shall be liable for any delay or failure to perform caused by circumstances beyond its reasonable control.”
This is short and that is its weakness. It does not list events, so every dispute becomes an argument about whether the event is “beyond reasonable control”. It has no notice requirement, no mitigation duty, and no end date. It does not say whether payments are covered. Courts will enforce this force majeure clause, but they will construe it narrowly, and the party claiming relief carries the argument.
2. A balanced services force majeure clause
“A party (the ‘Affected Party’) shall not be in breach of this Agreement to the extent that performance is prevented by a Force Majeure Event. ‘Force Majeure Event’ means an event beyond the reasonable control of the Affected Party, which it could not have avoided by reasonable precautions, including act of God, flood, fire, epidemic declared by a government authority, war, terrorism, lawful government order, and failure of public utilities. It does not include (a) changes in market conditions or cost of performance, (b) a failure of the Affected Party’s subcontractors unless caused by a Force Majeure Event, or (c) lack of funds. The Affected Party shall give written notice within seven days, describing the event, the obligations affected, and the expected duration, and shall use reasonable efforts to mitigate and to resume performance. Payment obligations for goods and services already delivered are not suspended. If the Force Majeure Event continues for more than 90 days, either party may terminate by written notice without liability for the period after the event began.”
This clause lists events, excludes the usual abuses (cost, funds, subcontractors), requires notice and mitigation, protects payments already due, and gives a way out. “Prevented” is a deliberate choice; “hindered” would let more claims through.
3. Supply or commodity contract, with hardship
“If a Force Majeure Event or a Change in Law materially increases the cost of supply by more than 15%, the parties shall negotiate in good faith for 30 days an equitable adjustment of price. If no agreement is reached, the Buyer may terminate the affected deliveries without penalty.”
Energy Watchdog is the lesson. Cost increases are not force majeure, so if the business wants relief from price shocks, it must write a price-adjustment or hardship mechanism. The same case turned on the definition of “Law”: if you want sanctions, tariffs or foreign legislation to count as change in law, say so, because a definition limited to Indian law will leave them out. The 15% and 30 days are illustrative. Choose figures that fit your margins.
4. A SaaS and cloud force majeure clause
“Force Majeure Events include widespread internet or power failure, denial-of-service or other cyber attacks that could not have been prevented by commercially reasonable security measures complying with Section [x], and failure of a third-party cloud host. Vendor may not rely on this clause for a failure caused by its own failure to maintain the security, backup and disaster recovery measures required by this Agreement.”
The second sentence is the one customers should insist on. A vendor that skipped patching cannot blame a cyber attack. Data-breach duties and penalties sit elsewhere; see our notes on DPDP contract clauses and the AI indemnity trap for how those link to liability. The risk allocation between this clause and the indemnification clause matters too: decide whether an indemnity survives a force majeure event, and say it.
5. Employment, consulting or freelance work
“Neither party is liable for delay caused by a Force Majeure Event. If the Consultant is unable to perform for more than 30 consecutive days because of such event, either party may terminate, and the Company shall pay fees for work completed up to the date of the event.”
For short engagements, a short window and a clear payment rule matter more than a long list of events. See our guide to freelance agreement clauses, and note that a client’s refusal to pay because of a downturn is a separate problem covered in what to do when a client refuses to pay.
Drafting checklist for a force majeure clause
Events. List them, and add a general catch-all. Think about epidemics, war and armed conflict, sanctions and trade restrictions, tariffs and embargoes, lawful government orders, strikes (outside the party’s own workforce), natural disasters, cyber attacks, and failure of utilities. Add anything specific to your industry.
Exclusions. State plainly that these do not count: increased cost or price, lack of funds, market changes, the party’s own fault, and subcontractor or supplier failure unless the failure is itself caused by a force majeure event.
Causation word. Choose between “prevents”, “delays” and “hinders”. Each gives a very different clause. Prevention is the strictest and the safest for the party receiving performance.
Notice. Say who gives it, to whom, in what form and within how many days. Include the description of the event, the obligations affected, the expected duration and the steps being taken. Notice requirements are enforced: in Rashmi Cement the absence of notice mattered, and MEP Infrastructure is the exception that proves it, since the court excused lateness only because the other side had acknowledged the event.
Evidence. Ask for supporting documents and regular updates, plus a notice when the event ends.
Mitigation. Require reasonable efforts to resume. Define what counts as reasonable so it does not mean “any alternative at any cost” or “nothing”.
Effect. Suspension, extension of time, or excuse. Say whether time-extension costs are borne by either party.
Payments. Say whether payment obligations are suspended. If they are not, state it. If rent or milestone payments are partly abated, state the formula.
Long-stop. A termination right after a fixed period; 60 to 90 days is common. Without it you can be locked into a dead contract. Termination is not automatic under most clauses or at law, so write the mechanism.
Change in law and hardship. Define “Law” to include foreign measures if you need them. Provide a renegotiation window and a fallback.
Insurance. Align it with the clause, including business interruption cover, and say who bears uninsured losses.
Dispute process. Provide for arbitration or an expedited expert determination for the question “did a force majeure event occur, and for how long”. The Delhi High Court said in the AAI matter that these are questions of fact for the tribunal.
If you have to invoke a force majeure clause, this is the order
- Read the clause today. Not tomorrow. Check the event definition, the notice period and the termination threshold.
- Write the notice. Short, factual, no admissions. State the event, the obligations affected, the date it began and the expected duration. Send it the way the contract requires, and keep proof of delivery.
- Gather evidence that connects the event to the failure: government orders, port notices, supplier letters, photographs, logs.
- Mitigate and record it. Quotes from alternate suppliers, rerouting options, requests to the other side. Keep the paper trail.
- Keep performing what you still can. A party that stops everything because one part is affected is inviting a counter-claim.
- Update regularly and give notice when the event ends.
- Do not treat it as a bargaining chip. An invocation that fails can itself be a wrongful non-performance.
If you are on the receiving end of a notice, respond in writing, ask for the evidence, reserve your rights, and check whether the supplier was already late. Halliburton is the case to cite.
War, sanctions and tariffs, briefly
These are the questions of 2025 and 2026. Indian courts have not given a single clear answer, but the direction is visible. A war in a region does not excuse a party in another country; the claimant must show how it prevented this contract. Sanctions that make payment or procurement difficult have been treated as difficulty rather than impossibility (Phosphate Company). Tariffs normally raise cost rather than prevent performance, which puts them in the Energy Watchdog camp unless the contract names them or provides price adjustment. Commentators also note that foreseeability weakens a claim: US tariff escalation has been public since 2018, so a contract signed after that date will find it harder to argue the risk was unforeseen. Law-firm commentary on the 2026 Gulf conflict stresses that contracts dependent on affected routes have a stronger claim than those with a remote link, and that the party must still pursue reasonable alternatives.
One question remains open: when a foreseeable risk stops being a force majeure event. Draft around it by naming the risk and saying what happens.
Common mistakes
Copying a template from a different industry. A construction force majeure clause on a software contract lists events that do not matter and omits the ones that do.
Relying on “act of God” alone in a force majeure clause. It is a narrow, old phrase and it will not stretch to a pandemic, cyber attack or sanctions.
Forgetting the other side’s conduct. A force majeure clause that helps you as a seller works against you as a buyer. Read it from both directions before you sign.
No termination right in the force majeure clause. The most common gap, and the most expensive.
Treating notice as a formality. It is often a condition. Missing it can lose a valid claim.
Not telling your insurer. Check the notification terms in your policy.
If you want help with a specific contract, contact us, or start with our legal checklist for Indian startups, the contract law glossary and the wider startup legal resources.
Frequently asked questions
1. What is a force majeure clause in simple words?
A force majeure clause is a contract term that excuses a party from performing, for as long as an event outside its control prevents performance. It lists the events that count, sets out notice and mitigation duties, and says what happens if the event goes on, usually a right to terminate.
2. Is a force majeure clause defined in Indian law?
Not by statute. India treats a force majeure clause as a contingent contract under Section 32 of the Indian Contract Act, 1872, and enforces it as written. Without a clause, a party relies on Section 56 (frustration), which applies only where performance becomes impossible or unlawful.
3. What is the difference between a force majeure clause and frustration?
Force majeure comes from the contract and normally suspends or excuses performance while the event lasts. Frustration comes from Section 56 and makes the contract void from the moment of impossibility, with restitution under Section 65. Where a force majeure clause covers the event, Energy Watchdog v. CERC says the clause governs.
4. Does a price increase count as force majeure?
No, not unless the contract says so. In Energy Watchdog, rising coal prices did not qualify, and in Alopi Parshad the Supreme Court said that onerous performance does not discharge a contract. If you want relief from price shocks, write a price-adjustment or hardship clause.
5. Did COVID-19 count as force majeure in India?
Sometimes, and only on the facts. Claims succeeded where the clause covered epidemics and the party showed actual prevention, as in the DIAL concession (Delhi High Court, 2025). They failed where performance was not really prevented (Standard Retail, Steel Authority v. Norvic Shipping) or where the party was already in default (Halliburton v. Vedanta).
6. Does force majeure excuse payment of rent or dues?
Usually not. Payment is rarely “prevented” by an event. Courts have separated physical performance from payment for goods already supplied (GEA EGI v. BHEL). Unless the force majeure clause or a rent-abatement provision covers it, the obligation continues.
7. Is notice mandatory under a force majeure clause?
If the clause requires notice, treat it as mandatory. Late or missing notice can defeat a claim (Rashmi Cement). The one case where late notice was excused (MEP Infrastructure) turned on the other side having acknowledged the event.
8. Can I terminate a contract under a force majeure clause?
Only if the clause gives you the right or if the contract is frustrated under Section 56. Most clauses allow termination after a fixed period, commonly 60 to 90 days. Termination is not automatic, and a wrongful termination can itself be a breach.
9. Are war, sanctions and tariffs force majeure events?
Only if the clause names them or the general words cover them, and only if they actually prevent performance. Indian cases treat sanctions and tariffs mostly as difficulty or cost rather than impossibility. Define them expressly and add a change-in-law and price-adjustment mechanism.
10. Can government circulars or notifications support a force majeure claim?
For government contracts, sometimes. In MEP Infrastructure the Delhi High Court relied on a 19 February 2020 circular. Other benches, in Rashmi Cement and Polytech Trade, held circulars and advisories do not bind private contracting parties. The force majeure clause in your contract remains the main source of relief.
This article is general information, not legal advice. Check your contract and the current law, or take advice before invoking or drafting a clause.